The team wants to estimate the time required for one tester to perform four test...

✅ The verified answer to this question is available below. Our community-reviewed solutions help you understand the material better.

The team wants to estimate the time required for one tester to perform four test cases related to a software module. The following labor time measures for performing a single test case have been determined:

Most optimistic scenario: 1 hour

Most pessimistic scenario: 8 hours

Most likely scenario: 3 hours

What is the final time estimate required to perform all four test cases assuming the use of the three-point estimation technique?