A project activity has an optimistic time estimate of 2 weeks, a most likely est...
✅ The verified answer to this question is available below. Our community-reviewed solutions help you understand the material better.
A project activity has an optimistic time estimate of 2 weeks, a most likely estimate of 4 weeks, and a pessimistic estimate of 6 weeks. What is the expected activity duration?