A company pays R300 000 to replace a major component of a factory machine. The f...

✅ The verified answer to this question is available below. Our community-reviewed solutions help you understand the material better.

A company pays R300 000 to replace a major component of a factory machine. The faulty component that is replaced is sold for R15 000. The carrying amount of the machine just before this replacement occurs is R3 375 000, of which R75 000 relates to the faulty component that is being replaced. The revised carrying amount of the machine after the replacement occurs and the profit or loss on disposal of the faulty component are: