What is the minimum total weight of unscheduled tasks when there is one processor, no preemption is allowed, and there are 8 tasks with equal lengths (li) of 2, with given weights and deadlines as follows: t1: (w1 = 2, d1 = 10), t2: (w2 = 3, d2 = 12), t3: (w3 = 8, d3 = 6), t4: (w4 = 6, d4 = 4), t5: (w5 = 5, d5 = 2), t6: (w6 = 4, d6 = 4), t7: (w7 = 10, d7 = 8), t8: (w7 = 12, d7 = 6)?